Builder Not Giving Possession? Your RERA Rights as a Homebuyer, Explained Step by Step

When a builder misses the possession date, the law does not leave you without a remedy. The Real Estate (Regulation and Development) Act, 2016 (RERA) gives a homebuyer two clear choices under Section 18: either withdraw from the project and claim a refund of everything paid, with interest, or hold on to the flat and claim interest for every month of delay. This guide explains how that right works in practice, what a RERA complaint involves, and what to do first.
What RERA says when possession is delayed
Section 18 applies to projects that are registered with a state RERA authority. If the promoter (the builder) fails to complete the project or hand over possession by the date agreed in the agreement for sale, the buyer may:
- Claim a refund of the amount paid, with interest at the rate the rules prescribe; or
- Continue with the project and claim interest for the period of delay until possession is actually handed over.
A third situation arises if the builder's registration is suspended or revoked, or if the builder abandons the project. In that case, the buyer's right to a refund with interest is even clearer.
The Supreme Court has repeatedly held that the right to refund is not a discretionary favour — it is a statutory entitlement once delay is established. A builder cannot force you to accept a flat years later simply because construction eventually finished.
The two options: refund or possession with interest
Many buyers assume they must choose one path at the start and cannot change course. That is not quite right. In practice, a buyer may initially press for possession and later seek a refund if the delay becomes indefinite — the RERA authority will look at the facts.
A common mistake is to accept a fresh "grace period" letter from the builder without recording that it is without prejudice to your right to claim delay interest. Signing such letters can later be used to argue that you waived your claim. Consider the situation: a buyer receives a letter extending possession by twelve months. He signs and returns it because he wants the flat. Two years later, at the hearing, the builder produces that letter and says the buyer accepted the revised date. The buyer then has to explain why his conduct should not amount to acceptance. It is a needless fight.
The safer approach: if you sign anything, add a line stating that you do not waive your right to compensation or interest for the earlier delay.
How to file a complaint — step by step
Step 1: Check your documents and the delay.
You need the agreement for sale, the payment receipts, the builder's allotment letter, and any communication about the revised possession date. Confirm the exact date on which possession was promised and the date on which it was actually due. Locate the project's RERA registration number — it appears on the agreement and on the state RERA portal.
Step 2: Send a written notice to the builder.
This is not mandatory in every state, but it is good practice and often a precondition in the rules. The notice should set out the agreed possession date, the delay, the amount paid, and what you want — either possession with delay interest or a refund. Keep proof of dispatch.
Step 3: File a complaint before the state RERA authority.
Under Section 31, a buyer may file a complaint with the RERA authority where the project is registered. Most states allow online filing. The complaint should be concise: facts, the relief sought, and the documents relied on. You do not need to draft it like a plaint in a civil suit, but it must be clear and supported by an affidavit in the format the authority prescribes.
Step 4: Attend the hearings.
The authority will issue notice to the builder and list the matter. Hearings are usually before a single member or a bench. The builder may seek adjournments; keep a record of every date. If the builder fails to appear, the authority may proceed ex parte.
Step 5: The order and its enforcement.
If the authority finds delay, it can direct a refund with interest, or possession with interest for the delay period. If the builder does not comply, the order can be enforced under Section 40 of RERA, which treats non-compliance as an offence. You may also file an execution application before the RERA authority or, in some states, before the civil court.
Step 6: Appeal, if needed.
An appeal against a RERA order lies to the Real Estate Appellate Tribunal under Section 44, usually within sixty days. The tribunal may condone further delay if there is sufficient cause.
What interest rate applies, and on what amount
RERA does not fix a single national rate. Section 18 refers to the rate prescribed by the rules framed by each state. Many states have adopted the State Bank of India's Marginal Cost of Funds Based Lending Rate (MCLR) plus a margin, often 2%. The exact rate differs, so check the rules of the state where your project is registered.
Interest is generally calculated on the amounts you have actually paid to the builder, from the date the possession became due until the date of refund or actual possession.
Registration and the occupancy certificate
Two practical points come up repeatedly.
First, if the project was not registered with RERA when it should have been, the builder has violated Section 3. You can still file a complaint; the authority can direct registration and take penal action.
Second, do not take possession without an occupancy certificate (OC) unless you have independent legal advice. Taking possession of an unapproved building can expose you to municipal action and make it harder to claim remedies later.
What courts actually look at
In practice, RERA authorities and the appellate tribunals focus on three things: the agreed date in the agreement for sale, proof of payment, and whether the delay is attributable to the builder. Force majeure claims — strikes, government sanctions, court stays — are examined closely. A builder who has collected your money and simply not finished the project will find it hard to justify years of delay.
What judges tend to find unconvincing: oral assurances of a new date, a brochure promising "possession soon", or a buyer's continued payment of instalments. The last point matters. Paying an instalment after the due date does not automatically mean you accepted the delay; the Supreme Court has said so in the context of homebuyer complaints. But it is a point the builder will raise, so be prepared.
What to do next
Gather your agreement for sale, payment receipts, the builder's possession letters, and any email or WhatsApp messages about the delay. Note the exact promised date and the date on which you actually paid each instalment. Send a written notice to the builder setting out your claim. Then file before the RERA authority of the state where the project is located — do not wait for the builder's oral assurances. If an order is already in your favour and the builder is not complying, move for enforcement under Section 40 without delay.
Facing a similar situation? Talk to a BKA advocate before you act.
Chat on WhatsAppNeed help with this?
Our Real Estate & RERA Disputes services
Frequently Asked Questions
Builder possession nahi de raha, main kya kar sakta hoon? (Builder is not giving possession, what can I do?)
You can file a complaint under Section 31 of RERA before the state authority where the project is registered, seeking either a refund with interest or possession with delay interest under Section 18. Gather your agreement, payment receipts and any possession letters first.
Can I claim both refund and possession at the same time?
No. Section 18 gives you an option — either withdraw and claim refund with interest, or continue with the project and claim interest for the delay. You must choose one in your complaint, though the authority may allow an amendment in appropriate cases.
How long does a RERA complaint take to decide?
The Act expects the authority to dispose of complaints within sixty days, but in practice it often takes longer. Delays usually come from adjournments sought by the builder. Keep track of hearing dates and press for early disposal.
What if the builder has abandoned the project or gone bankrupt?
Your right to a refund with interest becomes stronger. You can also seek action against the builder's registration under Section 7 and, in appropriate cases, approach the National Company Law Tribunal if insolvency proceedings have begun.
Do I need a lawyer to file a RERA complaint?
You can file yourself, but a lawyer helps with the drafting, the evidence, and the calculation of interest. If the amount is large or the builder is contesting, legal representation is advisable.
Related Articles

Domestic vs International Arbitration in India: Key Differences Every Business Should Know
Whether an arbitration counts as international under Indian law decides the governing rules, court powers and what the seat of arbitration means.

Mutual Consent Divorce in Delhi Family Courts: A Step-by-Step Guide to the Full Process
A mutual consent divorce in Delhi family courts needs a joint petition and two motions. The six-month wait can be waived in some cases.

Divorce in Rohini Family Court: A Step-by-Step Guide from Filing to Final Decree
Divorce at Rohini Family Court depends on territorial jurisdiction, the ground you plead and how mediation goes before evidence starts.